Saturday 29 June 2013

Progress Report 12

Telephone line

14 August 2012 

Installation of telephone pipe line by selected subcontractor. The service pipe line are installed by excavated the area for telephone pipe. All figure shows the process of the telephone pipe line installation. 


Figure 1: Service pipe

Figure 2: Excavate for service pipe 

Figure 3: Service pipe manhole

This process are done after a week, JC9C manholes are install before layering the pipe line. 

Aisyah Ibrahim 
20 August 2012

Wednesday 17 October 2012

Progress Report 11 (guard house)

Guard House 

1 August 2012 - on going 
This guard house basically using non-suspended slab and used micro fiber concrete to replace the BRC.                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                        

Firuge 1: Right view

Figure 2: Back view

Figure 3: Front view 

Figure 4: Right view

Aisyah Ibrahim 
28 August 2012 (4.58pm) 

Tuesday 28 August 2012

Overall Work 4

Overall work 4

Overall view of the site, 30% work done. 

Figure 1 : Front left view

Figure 2 : Front right view

Figure 3 : Back right view 

Figure 4 : Back left view

Aisyah Ibrahim 
29 August 2012 (8.32am) 

Monday 27 August 2012

Overall Work 3

8 August 2012

Overall view of the site 28% work had been done.

Figure 1 : Front right view

Figure 2 : Front view 

Figure 3 : Front left view 

Figure 4 : Back right view

Aisyah Ibrahim 
28 August 2012 (11.28am)

Sunday 26 August 2012

Site visit by Dato Hj Abd Rahman

7 August 2012

On Tuesday at 9.15am, Dato Hj Abd Rahman, the owner of Kumpulan Rahman Brothers (KRB) had visited the site. 
Figure 1: Get brief form En Zulhan, Site Supervisor Unijaya Teknologi Sdn Bhd
  
Figure 2 : Dato Hj Abd Rahman give motivational advice. 

Figure 3 : Dato Hj Abd Rahman with all the industrial trainee and Unijaya Teknologi Sdn Bhd Staff. 
  
Figure 4: Dato Hj Abd Rahman going back.

Aisyah Ibrahim 
27 August 2012 (10.16am) 

Tuesday 31 July 2012

Overall work 2

1 August 2012

Overall view on site, 25% progress work had been done.

Figure 1: Front right view

Figure 2: Back right view

Figure 3: Back left view 

Figure 4: Front left view 

Figure 5: Sewerage pipe in progress

Figure 6: Drainage in progress 
 
Figure 7: Column concreting in progress 

Aisyah Ibrahim 
1 August 2012 (12.38PM) 

Progress Report 10

4 July 2012 - On going 

Water floor trap, urinal pipe and Sewerage pipe 

All this pipe must individually pipe to make sure the flow well done. So the output didn't mix and effect when do the water treatment.  

Figure 1: Water floor trap 

Figure 2: Sewerage pipe

Figure 3: Manhole for sewerage

Figure 4: Urinal pipe 

Aisyah Ibrahim 
1 August 2012 (12.30PM)