Wednesday, 17 October 2012

Progress Report 11 (guard house)

Guard House 

1 August 2012 - on going 
This guard house basically using non-suspended slab and used micro fiber concrete to replace the BRC.                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                        

Firuge 1: Right view

Figure 2: Back view

Figure 3: Front view 

Figure 4: Right view

Aisyah Ibrahim 
28 August 2012 (4.58pm) 

Tuesday, 28 August 2012

Overall Work 4

Overall work 4

Overall view of the site, 30% work done. 

Figure 1 : Front left view

Figure 2 : Front right view

Figure 3 : Back right view 

Figure 4 : Back left view

Aisyah Ibrahim 
29 August 2012 (8.32am) 

Monday, 27 August 2012

Overall Work 3

8 August 2012

Overall view of the site 28% work had been done.

Figure 1 : Front right view

Figure 2 : Front view 

Figure 3 : Front left view 

Figure 4 : Back right view

Aisyah Ibrahim 
28 August 2012 (11.28am)

Sunday, 26 August 2012

Site visit by Dato Hj Abd Rahman

7 August 2012

On Tuesday at 9.15am, Dato Hj Abd Rahman, the owner of Kumpulan Rahman Brothers (KRB) had visited the site. 
Figure 1: Get brief form En Zulhan, Site Supervisor Unijaya Teknologi Sdn Bhd
  
Figure 2 : Dato Hj Abd Rahman give motivational advice. 

Figure 3 : Dato Hj Abd Rahman with all the industrial trainee and Unijaya Teknologi Sdn Bhd Staff. 
  
Figure 4: Dato Hj Abd Rahman going back.

Aisyah Ibrahim 
27 August 2012 (10.16am) 

Tuesday, 31 July 2012

Overall work 2

1 August 2012

Overall view on site, 25% progress work had been done.

Figure 1: Front right view

Figure 2: Back right view

Figure 3: Back left view 

Figure 4: Front left view 

Figure 5: Sewerage pipe in progress

Figure 6: Drainage in progress 
 
Figure 7: Column concreting in progress 

Aisyah Ibrahim 
1 August 2012 (12.38PM) 

Progress Report 10

4 July 2012 - On going 

Water floor trap, urinal pipe and Sewerage pipe 

All this pipe must individually pipe to make sure the flow well done. So the output didn't mix and effect when do the water treatment.  

Figure 1: Water floor trap 

Figure 2: Sewerage pipe

Figure 3: Manhole for sewerage

Figure 4: Urinal pipe 

Aisyah Ibrahim 
1 August 2012 (12.30PM) 

Progress Report 9

27 July - On going

Sewerage pipe installation

This process must be done by specialist pipe installer because this pipe need accurate level and position to make sure the flow are smooth. Here we used Sunway SK Keramo pipe and bedding class A because all the pipe are under road.

Figure 1: Design for the sewerage bedding 

Figure 1.1: Sunway SK Keramo pipe

Figure 2: Excavate the soil  

Figure 3: Fill with crusher run 

 
Figure 4: Installation sewerage pipe

Figure 5: Concrete the connection 

Figure 6: Grease used at the connected end 

Figure 7: Sewerage pipe with crusher run 

Figure 8: Sewerage pipe with crusher run


Aisyah Ibrahim
1 August 2012 (11.14AM) 

Progress Report 8

17 July - On going

Drainage


Here we used 600mm width concrete drain (300mm half round glaze ware drain). Before install the U-drain, the brick wall and concreting the drain base must do first. So after all the work done the U-drain will be install and then concreting the sump and top of the drain.  

Figure 1: Concreting drainage 

Figure 2: Concreting drainage 


Figure 3: Bricklaying drainage

Figure 4: Complete Brick wall for drainage

Aisyah Ibrahim 
1 August 2012 (10.58AM) 

Progress Report 7

19 July - On going

Column

For this process rebar for column will be erected first then the form work. Form work must be erect accurately to make sure that the column are straight. The column concreted in two phase, only 12 column be concrete in one time because form tie to lock the form work not enough for all column.

Figure 1: Rebar for column

 
Figure 2: Erected column


Figure 3 : Front right area

Figure 4: Front left area

Figure 5: Back left area 

Aisyah Ibrahim 
1 August 2012 (9.08AM)

Tuesday, 24 July 2012

Overall work 1

25 July 2012

Overall view on the site, 15% progress work had been done.

Figure 1: Back right

Figure 2: Front right 

Figure 3: Front left 

Figure 4: Back left 

Progress Report 6

13 July 2012 - On going

Guard House 


Before concrete,
Figure 1: Form work for foundation 

Figure 2: Form work for foundation 

After concrete,
Figure 3: Foundation at guard house

Figure 4: Compaction area 

Figure 5: Compaction Process 

Aisyah Ibrahim 
25 July 2012 (10.44AM)