Column
For this process rebar for column will be erected first then the form work. Form work must be erect accurately to make sure that the column are straight. The column concreted in two phase, only 12 column be concrete in one time because form tie to lock the form work not enough for all column.
Figure 1: Rebar for column
Figure 2: Erected column
Figure 3 : Front right area
Figure 4: Front left area
Figure 5: Back left area
Aisyah Ibrahim
1 August 2012 (9.08AM)