Progress Report 3

29 May to 14 June 2012

Concreting Foundation

The process start when the concrete arrived from batching plant. G 30 Normal JKR mix propotion had been used for the concrete the foundation. The area of concreting are 1-5/A-J. The slump test allowable are 75mm +/- 25mm. The slump test had been done by the technician of the concrete batching plant. Process of the concreting take several hours to be done.

Figure 1: Slump Test for concrete. 

 
Figure 2: Concreting foundation

 
Figure 3: Vibrating the concrete

Figure 4: Final touch up for foundation


Figure 5: Final result for foundation 