Tuesday 31 July 2012

Overall work 2

1 August 2012

Overall view on site, 25% progress work had been done.

Figure 1: Front right view

Figure 2: Back right view

Figure 3: Back left view 

Figure 4: Front left view 

Figure 5: Sewerage pipe in progress

Figure 6: Drainage in progress 
 
Figure 7: Column concreting in progress 

Aisyah Ibrahim 
1 August 2012 (12.38PM) 

Progress Report 10

4 July 2012 - On going 

Water floor trap, urinal pipe and Sewerage pipe 

All this pipe must individually pipe to make sure the flow well done. So the output didn't mix and effect when do the water treatment.  

Figure 1: Water floor trap 

Figure 2: Sewerage pipe

Figure 3: Manhole for sewerage

Figure 4: Urinal pipe 

Aisyah Ibrahim 
1 August 2012 (12.30PM) 

Progress Report 9

27 July - On going

Sewerage pipe installation

This process must be done by specialist pipe installer because this pipe need accurate level and position to make sure the flow are smooth. Here we used Sunway SK Keramo pipe and bedding class A because all the pipe are under road.

Figure 1: Design for the sewerage bedding 

Figure 1.1: Sunway SK Keramo pipe

Figure 2: Excavate the soil  

Figure 3: Fill with crusher run 

 
Figure 4: Installation sewerage pipe

Figure 5: Concrete the connection 

Figure 6: Grease used at the connected end 

Figure 7: Sewerage pipe with crusher run 

Figure 8: Sewerage pipe with crusher run


Aisyah Ibrahim
1 August 2012 (11.14AM) 

Progress Report 8

17 July - On going

Drainage


Here we used 600mm width concrete drain (300mm half round glaze ware drain). Before install the U-drain, the brick wall and concreting the drain base must do first. So after all the work done the U-drain will be install and then concreting the sump and top of the drain.  

Figure 1: Concreting drainage 

Figure 2: Concreting drainage 


Figure 3: Bricklaying drainage

Figure 4: Complete Brick wall for drainage

Aisyah Ibrahim 
1 August 2012 (10.58AM) 

Progress Report 7

19 July - On going

Column

For this process rebar for column will be erected first then the form work. Form work must be erect accurately to make sure that the column are straight. The column concreted in two phase, only 12 column be concrete in one time because form tie to lock the form work not enough for all column.

Figure 1: Rebar for column

 
Figure 2: Erected column


Figure 3 : Front right area

Figure 4: Front left area

Figure 5: Back left area 

Aisyah Ibrahim 
1 August 2012 (9.08AM)

Tuesday 24 July 2012

Overall work 1

25 July 2012

Overall view on the site, 15% progress work had been done.

Figure 1: Back right

Figure 2: Front right 

Figure 3: Front left 

Figure 4: Back left 

Progress Report 6

13 July 2012 - On going

Guard House 


Before concrete,
Figure 1: Form work for foundation 

Figure 2: Form work for foundation 

After concrete,
Figure 3: Foundation at guard house

Figure 4: Compaction area 

Figure 5: Compaction Process 

Aisyah Ibrahim 
25 July 2012 (10.44AM) 

Wednesday 18 July 2012

Progress Report 5

12 - 15 July 2012

Ground Slab


For ground slab, the consultant used non suspended slab because the soil are hard enough to transfer load. Ground slab materials use micro synthetic fiber for concrete not BRC as usual. The micro synthetic fiber strength merely the same using BRC.

Figure 1: Non- suspended Ground Slab

Figure 2: Micro Synthetic fiber for concrete

Figure 3: Compacted Soil 
Before Concrete
Figure 4: Back left area

Figure 5: Back right area

Figure 6: Front left area

Figure 7: Concreting Ground Slab

Figure 8: Concreting Ground Slab

Figure 9: Lean concrete
After concrete
Figure 10: Front right area

 
Figure 11: Front left area

Aisyah Ibrahim
19 July 2012 (11.24 PM)

Monday 9 July 2012

Progress Report 4

17 April - 2 May 2012


Temporary Earth Drain 


 This temporary earth drain is used as drain to flow water inside the construction area. This to avoid any flood during construction.
Figure 1: Temporary Earth Drain process 

Figure 2: Temporary Earth Drain process 

Figure 3: Temporary Earth Drain Process 

Figure 4: Temporary Earth Drain process 

Aisyah Ibrahim 
9 July 2012 (4.33PM)